Project Details for
Water Street by the Park- Foundation Piles
Water Street By the Park
KELOWNA, BC
The site is located in Kelowna, BC, bounded by Water Street to the East and Leon Avenue to the South. The project scope included foundations piles for two towers part of a multi-phase mixed-use development.
Start Date | Fall 2022 |
Completion Date | Spring 2023 |
Contract Value | $5 – $10 Million |
Client Name | Amega Group |
Owner |
Project Highlights
- Pre-production static compression pile load testing program (8MN).
- 547 no. full displacement piles (FDP) of 600mm diameter to depths of 36.5m installed from base of 5m deep excavation.
- Displacement piling reduced approximately 6,500m3 of drilling spoil disposal compared to conventional concrete piling techniques.
- Challenging ground conditions encountered during construction, with Hall introducing pre-drilling of pile locations to improve schedule.